Training Lifecycle & Checkpoints

A training run does not have to reach total_steps to be useful. This page covers what each control actually does to your artifacts, how to keep the SAE from a run you stop early, and how to reclaim the disk that checkpoints accumulate.

What a training produces

A run writes two different things, and the distinction matters:

ArtifactPathWho reads it
Checkpointstrainings/{id}/checkpoints/checkpoint_{step}/the training loop, to resume
Community Standard exporttrainings/{id}/community_format/everything else

Feature extraction, SAE import, steering, circuit capture and Neuronpedia export all read the export, never the checkpoints. A run with checkpoints but no export has weights on disk that no other part of miStudio can open.

A multi-layer run writes one checkpoint per layer per step, all inside a single checkpoint_{step}/ directory. A three-layer run saving every 2,000 steps produces three files per save.

The controls

ControlEffect on the runEffect on artifacts
Pausesuspends; GPU is freednothing written
Resumecontinues from where it pausedresumes from the latest checkpoint
Stopends the run as cancelledno export is written
Stop & Finalizeends the run and exportsexport written from the newest checkpoint
Finalize(on an already-stopped run)export written from the newest checkpoint
Stop alone does not save an importable SAE

Stop ends the run and leaves its checkpoints in place, but it does not write the Community Standard export. The SAE will not appear under Import to SAEs. If you want to keep the model, use Stop & Finalize — or use Finalize afterwards, which does the same thing for a run you already stopped.

Stopping a run and keeping its SAE

The usual reason to stop early is that the run has converged: FVU has flattened and further steps are buying little. See SAE Training for reading those metrics.

Click Stop & Finalize. miStudio stops the run, rebuilds the SAEs from the newest complete checkpoint, and writes community_format/. The work runs on the CPU, so it does not queue behind GPU jobs, and it takes a few minutes for a large multi-layer run.

When it finishes the card shows Completed with an amber Finalized early @ N badge, and Import to SAEs becomes available.

Why it says "Completed"

Completed is what unlocks the SAE import path, so a finalized run has to carry it. But the run genuinely did not reach total_steps, so miStudio does not pretend otherwise:

  • the progress bar keeps its real value (a run stopped at 20% still shows 20%)
  • finalized_from_step records the checkpoint step it was built from
  • the amber badge states it plainly

If you see Finalized early @ 10,000 on a run configured for 50,000 steps, that SAE is the step-10,000 weights. That is usually exactly what you wanted — but it should never be a surprise.

Rescuing an already-stopped run

Runs stopped before this feature existed still have their checkpoints. Open the run and click Finalize. Same result: the export is written and the SAE becomes importable.

Failed runs also offer Finalize when they have checkpoints. Because a crashed run's checkpoints may predate whatever went wrong, miStudio asks you to confirm before building from them.

Choosing a checkpoint

Finalize uses the newest complete checkpoint step by default.

"Complete" matters for multi-layer runs: if a run was terminated while saving, the newest step can be missing some of its layers. Exporting that would give you a partial SAE presented as a whole one, so miStudio skips it and falls back to the newest step that has every layer, noting the skip in the logs.

Checkpoint retention

Checkpoints accumulate. A 50,000-step run saving every 2,000 steps across three layers writes 75 files; at ~1.1 GB each that is a large multiple of the exported SAE you actually use.

Once a run has produced its export, its intermediate checkpoints are only useful for resuming. Retention prunes them under a policy you control, in Settings → Storage.

The policy

SettingDefaultMeaning
Enable scheduled pruningoffrun the daily sweep at all
Dry runonreport what would be deleted, delete nothing
Always keep the best checkpointonnever delete the lowest-loss checkpoint
Keep most recent steps2how many newest steps to preserve
Minimum age (hours)24never prune anything younger

What is never deleted

Regardless of policy, pruning will not touch:

  • the best (lowest-loss) checkpoint, while that setting is on
  • the newest step, so a run stays resumable
  • any checkpoint of a run that is pending, initializing, running or paused
  • anything younger than the minimum age

Pruning also operates on whole steps. It never deletes some layers of a step and leaves others, because a partial step cannot be loaded.

Reviewing before deleting

Deletion is permanent, so the shipped defaults do nothing until you change them.

  1. Open Settings → Storage
  2. Pick a training and click Preview — a read-only report of the steps that would be pruned, the steps that would be kept, and the space it would free
  3. If it looks right, use Prune now for that one training, or enable the scheduled sweep

Leave Dry run on until you have read a report you are happy with. Turning it off is what makes the next run delete files.

Best ≠ last

For SAE training the lowest-loss checkpoint is frequently not the final one. Keeping "last N" alone can discard your best weights, which is why Always keep the best checkpoint is on by default.

Deleting a single checkpoint

Individual checkpoints can be deleted from the Checkpoints panel on a training card. Deleting the best checkpoint asks for confirmation first.

Troubleshooting

"Import to SAEs" is missing on a stopped run. No export was written. Click Finalize.

Finalize reports the step is incomplete. The newest checkpoint is missing layers, usually because the worker was terminated mid-save. Finalize normally falls back automatically; if every step is incomplete, the message lists the steps present on disk.

A prune reported 0.00 GB freed. Either nothing was eligible — check the preview — or files could not be deleted (permissions, a read-only mount). The run reports a files_failed count in that case, and the rows are deliberately kept so a later prune can retry.

A run shows "Finalized early" but I expected a full run. It was stopped or crashed before total_steps. The badge shows the step its weights come from.

See also